TriLink

TriLink BioTechnologies – (2) GMP +4 / -20 deg C ‘combo’ cold / freezer rooms in a Grade C space.

Requirement

Design build two GMP (2) +4 / -20 deg C cold / freezer rooms with +/- 1 deg uniformit.

Challenge

Schedule demanded installation on both floors (1st and 2nd) simultaneously to meet project turnover date. Coordinate installation in an existing building with space constraints.

Solution/Accomplishment

Collaborated with trades in BIM and on site to avoid any clashes during installation. Staffed project with multiple Foreman’s to meet the clients required turnover date.